RFP Tab 3 deliverables · Tab 5(e) timeline · Section B.5 schedule

January 1 to April 16, with the May 1 date protected.

The agreement gives the study four and a half months. The plan below puts the Committee's decisions early, runs the analysis while those decisions are tested, and leaves two weeks of float before May 1 for presidential review.

Phase 1 · Set the rules and get the data

Mon Jan 4 to Fri Jan 22, 2027
Kickoff with the Salary Equity Committee

Confirm the criteria the Committee has adopted, the meeting rhythm, and who speaks for the Committee between meetings.

Criteria workshop

The Committee chooses the service credit, the tolerance, the adjustment target, treatment of market hires and B+ contracts, and whether to run the optional sex and race or ethnicity check. Each choice is written into a criteria memo.

Data request and dictionary

One request to HR, field by field, with a template. Personal data travels by encrypted transfer only.

Milestone 1: approved criteria memo and data dictionary

Phase 2 · Build and validate the dataset; first findings

Mon Jan 25 to Fri Feb 19, 2027
Validation

Tie to payroll totals, reconcile column and credited-year codes against personnel files where they disagree, normalize B+ contracts to base, and record every correction.

Faculty information session 1

What the study is, what data it uses, and how the method works, before any results exist.

Both lenses run

Rule-based expected salaries and the statistical model, with diagnostics, reviewed by a second analyst.

Milestone 2: validated dataset and preliminary findings briefing

Phase 3 · Adjustments, costs and phasing

Mon Feb 22 to Fri Mar 19, 2027
Member-level results

Each flagged case reviewed against its record; borderline cases listed for the Committee with the evidence for each side.

Cost and phasing scenarios

Total cost with salary and employer-paid benefits; three funding scenarios (full, two-year, three-year) and a priority order for partial funding; a briefing for Executive Leadership.

Milestone 3: adjustment method, member results, cost scenarios

Phase 4 · Final report and member statements

Mon Mar 22 to Fri Apr 16, 2027
Final report

Method, data, findings, adjustments, costs, phasing, and at least one worked example, for Committee approval (RFP E.C.1.c).

Published method summary and statements

The plain-language summary the agreement requires, and an individual statement for every member in the analysis.

Milestone 4: final report approved by the Committee

Phase 5 · Results, appeals and handover

Apr 19, 2027 through the close of appeals
Faculty information session 2 and appeals support

Results explained; each appeal gets the member's full calculation and our written analysis within 10 business days.

Handover

Every file, script, model and template delivered to CSN in open formats so the FY29 study can rerun it.

Milestone 5: statements delivered, sessions held, appeals support complete

Day names checked against the 2027 calendar. If the Committee's own calendar moves a meeting, the plan moves with it; the April 16 completion date and the May 1 recommendation date do not.